02/10/2018 |
ADITIVO DE PRAZO |
10° ADITIVO CP 1905.02/2016 |
2018 |
MV & R LOCACAO E CONSTRUCAO EIRELI |
380.349,08 |
|
05/06/2018 |
ADITIVO DE ACRÉSCIMO |
9° ADITIVO CP 1905.02/2016 |
2018 |
MV & R LOCACAO E CONSTRUCAO EIRELI |
380.349,08 |
|
04/06/2018 |
ADITIVO DE PRAZO |
8° ADITIVO CP 1905.02/2016 |
2018 |
MV & R LOCACAO E CONSTRUCAO EIRELI |
359.405,43 |
|
06/02/2018 |
ADITIVO DE PRAZO |
7° ADITIVO CP 1905.02/2016 |
2018 |
MV & R LOCACAO E CONSTRUCAO EIRELI |
359.405,43 |
|
09/10/2017 |
ADITIVO DE PRAZO |
6° ADITIVO CP 1905.02/2016 |
2017 |
MV & R LOCACAO E CONSTRUCAO EIRELI |
359.405,43 |
|
06/06/2017 |
ADITIVO DE PRAZO |
5° ADITIVO CP 1905.02/2016 |
2017 |
MV & R LOCACAO E CONSTRUCAO EIRELI |
359.405,43 |
|
06/02/2017 |
ADITIVO DE PRAZO |
4° ADITIVO CP 1905.02/2016 |
2017 |
MV & R LOCACAO E CONSTRUCAO EIRELI |
359.405,43 |
|
14/10/2016 |
ADITIVO DE PRAZO |
3° ADITIVO CP 1905.02/2016 |
2016 |
MV & R LOCACAO E CONSTRUCAO EIRELI |
359.405,43 |
|
30/08/2016 |
ADITIVO DE PRAZO |
2° ADITIVO CP 1905.02/2016 |
2016 |
MV & R LOCACAO E CONSTRUCAO EIRELI |
359.405,43 |
|
05/07/2016 |
ADITIVO DE PRAZO |
1° ADITIVO 1905.02/2016 CP |
2016 |
MV & R LOCACAO E CONSTRUCAO EIRELI |
359.405,43 |
|